Indiana Construction Litigation Hold
IN Code § 32-30-1-5 (2022):
No action can be taken unless commenced within:
1) 10 years after substantial completion.
2) 12 years after completion and submission of plans.
Whichever date occurs earlier.
State Statute for Construction: 10 Years
*The National Society of Professional Engineers Recommends an Additional: 3 Years
Recommended Document Retention 13 Years
If you would like to learn the statute of limitations of any warranty your state entitles you to, refer to our Warranties map.