South Dakota Statute of Limitations

South Dakota Construction Litigation Hold

SD Codified : § 15-2A-3 (2022):

No action can be taken more than 10 years after substantial completion.

SD Codified L § 15-2A-5 (2022):

If injury to property, person, or wrongful death occur in the 10th year, action may be brought within 1 year, but may not exceed 11 years after substantial completion.

Online Reference

National Society of Professional Engineers Home 

State Statute for Construction: 10 Years
*The National Society of Professional Engineers Recommends an Additional: 3 Years

Recommended Document Retention 13 Years